Pradeep Patil
https://www.linkedin.com/in/pradeep-patil-8a78b667/
Industrial Engineer with total 8 year of industrial experience
Pune, Maharashtra, India
Forbes Marshall
Pune Area, India
Industrial Engineer
Jul 2014 – Present (2020)
Expansion of Krohne Marshall factory
Managed to increase the capacity by 40% for three products line of flow meters.
Installed 34 Assembly workstations, more than 50 racks, material handling conveyors.
Layout modification for three products line & raw material store modification.
Achieved 30% reduction in distance travel & 17% increase in productivity.
Productivity improvement for DCEM
Detailed time study and method study, layout modification, material storage and WIP racks.
Process improvement using hand tools, power tools, enhanced 5S and visual management.
Resulted in 21% productivity improvement.
Awarded FM Star of the month & appreciated by the division Manager.
Productivity Improvement : Valve Assembly Line-2
Elemental analysis based on video study conducted using WorkPro.
Improvement in material handling, layout modification and process improvements.
20% increase in productivity, 33% reduction in area, material handling time reduced by 27%.
Overall Layout Modification : FM Arca
Distance travel reduced from 2.5 to 1.6 Km, free space of 230 sq. m. made available, reduction
in transshipments by 16%.
Success Story of Industrial Engineer
24 June 2016
Isaac Mitchell, Director, Lean Continuous Improvement, East Tennessee Children’s Hospital. Bachelor of Science, Industrial Engineering, University of Tennessee
https://iiseblogs.org/2016/06/24/meet-isaac-mitchell/
https://iiseblogs.org/2016/07/08/meet-carl-jake-kirpes/
29 October 2020
25 June 2016
No comments:
Post a Comment